Sligo House, Watford.
The development of 32 flats plus 4,000m2 commercial unit to shell and core.




Private Residential
PC Q1 2024
£8,600,000.00
22 months completed in 19 months.
A logistically challenging site, located on Watford High Street with bus lanes, bus stops and positioned on one way ring road section. Sitting between two new developments, Boulevard Construction undertook in-depth party wall awards and Section 278 works to the highways to front of the property.
Boulevard Construction successfully submitted a section 73 planning application which resulted in the addition of 3 residential units. The scheme was successfully completed 3 months ahead of programme, on budget and with no contractor variations.